Tuesday, 20 May 2008
Station Road Swavesey
Once the Windmill Bridge is open again (currently scheduled for June) work will shift to Station Road in Swavesey. The contractors are looking at the least disruptive way of laying the concrete across the road. It is likely that the road will only be completely closed for a few weeks, rather than the months that happened nearer to Cambridge. The contractors hope to carry out all the utility diversions while keeping the road partially open. There will be access at all times for pedestrians and cyclists, which is essential for students going to the village college. Given the work being done at the same time at the guided busway junction with the B1050 as well as the long awaited Longstanton bypass, it is essential that roads are shut for as little time as possible. Once I have more information I will let you know